NEVADA SUPREME COURT CLARIFIES VALIDITY OF PAY-IF-PAID PROVISIONS

On March 24, 2022 the Nevada Supreme Court issued its decision in Helix Electric of Nevada v. APCO Construction, Inc., Case No. 77320 and further expounded upon the enforceability of pay-if-paid provisions as previously address in APCO Construction, Inc. v. Zitting Brothers Construction, Inc., 473 P.3d 1021 (2020).

The Court reiterated its prior holding that pay-if-paid provisions are not per se void in Nevada, however, such provisions will be deemed void if they require subcontractors to waive their rights under Nevada statutes requiring prompt payment or if they relieve general contractors from their obligations or liabilities under Nevada’s prompt payment statutes.  The Court, however, did note that an invalid pay-if-paid provision does not necessarily invalidate other contractual conditions precedent to payment and that those conditions may prevent payment to a sub-contractor.  Additionally, the Court noted that when a contract is assigned all rights arising under that contract are likewise assigned including, potentially, the right to payment for contractually withheld retention and attorneys’ fees, therefore, a subcontractor may not be able to look to the party with whom it had a contract for payment.

In the Helix Electric case, APCO Construction served as the general contractor on a construction project in Las Vegas, NV.  APCO Construction entered into a subcontract with Helix Electric (Helix) for certain work related to the project.  The contract allowed APCO to withhold from Helix retention in the amount of 5% of all billings.  Retention was to be released pursuant to the express terms of the contract only upon the occurrence of several conditions including APCO receiving payment from the project owner, Helix completing its work on the project, the owner accepting that work and Helix delivering close-out documents and claim releases.  Ultimately, the prime contract between APCO and the owner was terminated in August 2008.  Helix continued to do work for a new general contractor until December 2008 when the project ultimately failed, and all work ceased.  As a result of the project’s failure multiple lawsuits were filed and numerous contractors, including APCO and Helix, were left unpaid.

Among the lawsuits was one in which Helix sued APCO for work performed and accepted and unpaid retention.  At trial the district court found that the subcontractors of APCO, including Helix, had been assigned to the replacement general contractor and had continued to perform work.  Helix sought to collect retention for work performed under APCO pursuant to the subcontract in the amount of $505,021.  APCO refused to pay the retention on the basis that the conditions precedent to payment had not been met including the fact that work on the project was not complete, close out documents had not been provided or claim releases provided.  Helix argued that its contract with APCO was never officially terminated and therefore APCO remained liable for payment of withheld retention and that the conditions precedent were unenforceable because they were contained in the same portion of the contract that contained an invalid pay-if-paid provision and that under the Court’s prior ruling in Zitting Brothers Construction, conditions precedent to payment were void.  The district court held that although the pay-if-paid provision was void, the remaining conditions to payment were valid.

In reviewing the district court decision, the Nevada Supreme Court held that NRS 624.624(2)(b) explicitly allows a contractor to condition payment of retained funds upon the subcontractor supplying lien releases.  Likewise, the statute does not preclude the contractor from imposing other completion and acceptance conditions for payment. The Court further noted that such conditions went to the very purpose of retention which is to ensure completion of work by the subcontractor.  Additionally, the Court noted that the contract contained a “severability clause” such that if one provision of a contract is deemed unenforceable (such as pay-if-paid) that will not affect the enforceability of the remaining clauses in the contract. 

Likewise, the Court found that the subcontract between Helix and APCO had been assigned to the project’s new general contractor and that although Helix never signed a formal document it honored that assignment by continuing to perform work.  Since the contract was assigned to a new party all obligations and rights under that contract were likewise assigned.  As a result, Helix did not have any remaining rights to pursue against APCO since APCO was no longer a party to the contract.  This fact also worked against APCO as APCO sought a contractual award of attorneys’ fees in having had to defend the lawsuit.  The court ruled that just as Helix had to rights against APCO under the assigned contract, APCO had to rights against Helix and could not rely on the attorneys’ fees provision. In summary the case held that 1) pay-if-paid provisions are not per se invalid but will be very difficult to enforce; 2) an invalid pay-if-paid provision will not necessarily render unenforceable other conditions precedent to payment; and, 3) once a contract is assigned all rights and obligation follow the contract and may leave a subcontract without a remedy against the party it originally contracted with.

New Requirements for Residential Solar Contractors in Nevada

The following requirements must be included in all residential solar contracts pursuant to SB 303 which was passed in the 2021 Legislative Session:

  • Down payments must not exceed $1,000 or 10 percent of the aggregate total contract price, whichever is less, of any initial down payment or deposit paid or promised to be paid to the contractor by the owner of the single-family residence before the start of construction.
  • The estimated date of completion and a description of all work to be performed under the contract.
  • Changes in scope or price of the work to be performed under the contract must be agreed to in writing by both parties; change orders are not enforceable if not adhered to as directed.
  • New installation projects must include a plan and scale drawing showing the shape, size, dimensions, and specifications for the construction and equipment for work outlined in the contract.
  • Information about progress payments and commissioned salespeople.
  • Disclosure of the retail price of a kilowatt per hour, any offsetting tariff, and the identity of the provider-of-last-resort for the single-family residence at the time the contract is executed.
  • Statement that the contractor is responsible for the acts, statements, and representations (written or oral), of a sales representative used in the advertising, marketing, or sale of residential solar systems.
  • Notices informing consumers of the PUC, right to request performance bond, contact an attorney, or copy of the contract in the language used to explain the contract terms.
  • Contractor must obtain all necessary permits and approvals from the interconnecting electrical utility provider.

Violation of these statutes may result in discipline by the NSCB and may be reported to the Nevada Attorney General’s Office for a potential violation of the Deceptive Trade Practices Act. 

Nevada Supreme Court Rules on Validity of Pay-if-Paid Clauses

On October 8, 2020 the Nevada Supreme Court issued its decision in APCO Construction, Inc. v. Zitting Brothers Construction, Inc., Case No. 75197 and addressed the enforceability of pay-if-paid provisions in construction contracts.  In short, the Court held that pay-if-paid provision are not per se void in Nevada, however, such provisions will be deemed void if they require subcontractors to waive their rights under Nevada statutes requiring prompt payment or if they relieve general contractors from their obligations or liabilities under Nevada’s prompt payment statutes.  The practical effect of this ruling is to make enforcement of pay-if-paid provisions difficult and limits their applicability to very narrow circumstances which must be evaluated on a case by case basis.  Thus, general contractors should be cautious in relying on the validity of such provisions given their very narrow application and should take great care in drafting such provisions in any construction agreement.

In the APCO Construction case, APCO Construction served as the general contractor on a construction project in Las Vegas, NV.  APCO Construction entered into a subcontract with Zitting Brother Construction (Zitting) for certain work related to the project.  The contract required APCO to pay Zitting 100%  of work completed during the prior month (less retention) within 15 days of APCO receiving payment from the project owner.  Payment to Zitting was conditioned on APCO receiving payment from the owner.  This condition precedent also applied if the prime contract between APCO and the owner was terminated, thereby conditioning final payment to Zitting on APCO actually receiving final payment from the owner.  Ultimately, the prime contract between APCO and the owner was terminated in August 2008.  Zitting continued to do work for a new general contractor until December 2008 when the project ultimately failed, and all work ceased.  As a result of the project’s failure multiple lawsuits were filed and numerous contractors, including APCO and Zitting, were left unpaid.

Among the lawsuits was one in which Zitting sued APCO for work performed and accepted, unpaid retention and unpaid change orders.  In part, APCO raised the defense that the pay-if-paid provision of the contract meant that Zitting was not entitled to seeks damages from APCO because APCO had not been paid by the owner.  The district court granted partial summary judgment in favor of Zitting and found that pay-if-paid provisions were void and unenforceable under Nevada law. 

In reviewing the district court decision, the Nevada Supreme Court held that NRS 624.628(3) protects subcontractors’ rights by rendering void and unenforceable any agreement that requires a lower-tiered subcontractor to waive any rights provided by NRS 624.624 to 624.630, relieves a higher-tiered contractor of any obligation or liability imposed by NRS 624.624 to 624.630 or requires a lower-tiered subcontractor to waive, release or extinguish a claim or right for damages or an extension of time . . .  One of the rights protected is a subcontractor’s right to prompt payment as provided by NRS 624.624.[1]  In evaluating the specific terms of the contract at issue the Nevada Supreme Court held that the district court erred in concluding that all pay-if-paid provisions are void on their face, but did uphold the summary judgment and award of damages.  The Supreme Court found that the contract contained a schedule of payments that required payment to Zitting within 15 days of APCO receiving payment from the owner.  APCO argued that payment from the owner was a condition precedent to Zitting being entitled to payment.  This condition precedent prevented payment from ever being made to Zitting for work that was performed and accepted and for which payment would otherwise be due and owing.  The Nevada Supreme Court found that this violated Zitting’s right to prompt payment under NRS 624.624(1)(a).  Thus, although the parties agreed to the condition precedent in their written contract, the Nevada Supreme Court found the provision void as it interfered with payment rights guaranteed under Nevada law.

This raises the question of when a pay-if-paid provision will be enforced.  In citing to an unpublished decision (Padilla Const. Co. of Nev. v. Big-D Constr. Corp, (Case Nos. 67397 & 68683 (Order of Affirmance, Nov. 18, 2016)), the Nevada Supreme Court noted that if a subcontractor’s work is not accepted because it is defective and the owner withholds payment from the general contractor the general contractor may enforce a pay-if-provision.  The basis for this decision was that the work of the subcontractor was never accepted and therefore payment never became due.  This appears to be a very narrow exception to what should be interpreted as a broad public policy against pay-if-paid provisions. 

If you have questions about how this applies to you or your business, please contact us:

Brian J. Pezzillo, Esq., CIPP/E, CIPM

3800 Howard Hughes Pkwy., Ste. 1000

Las Vegas, NV 89169

bjp@h2law.com 702.667.4839


[1] NRS 624.624(1) states that if a written agreement contains a schedule of payments the higher-tiered contractor must pay the lower-tiered subcontractor: 1) on or before the date payment is due; or, 2) within 10 days of which the higher-tiered contractor receives payment – whichever is earlier.  NRS 624.624(1)(b) provides that if a written agreement contains no schedule for payment then the lower-tiered contractor must be paid within 30 days of submitting a payment request or 10 days of when the higher-tiered contractor receives payment – whichever is earlier.

Nevada Construction Law Book

NEW BOOK PROVIDES OVERVIEW OF LAWS COVERING THE CONSTRUCTION INDUSTRY IN NEVADA (TUESDAY, FEBRUARY 6, 2018)

Las Vegas, February 6, 2018: A new book providing an overview of laws and regulations governing the construction industry and design profession in Nevada is available. Nevada Construction Law is a 254-page volume co-authored by attorneys Brian Pezzillo and Jennifer Lloyd of Howard & Howard in Las Vegas.

The book is organized into 12 chapters covering a comprehensive range of the construction-related state laws, local city and county administrative codes and ordinances and interpretations of various related court rulings:

  1. Business Entity Types
  2. Licensing of Construction and Design Professionals
  3. Public Works Bidding
  4. Public Works Payment Remedies
  5. The Mechanic’s Lien in Nevada
  6. Private Works Payment Remedies
  7. Residential Construction
  8. Construction Lending
  9. Nevada Occupational Safety and Health
  10. Doing Business with Disadvantaged Enterprises
  11. Alternative Dispute Resolution

Our goal in preparing this book was to provide a one-stop, easy-to-access reference guide for any company or individual working in or providing services to the construction industry in Nevada,” said Pezzillo.
Published by ConstructionChannel.net and HLK Global Communications, the book is available at www.constructionchannel.net for $148 plus $7.45 shipping and handling.
About Howard & Howard
Founded in 1869, Howard & Howard is a full-service law firm with a national and international practice that provides legal services to businesses and business owners. The firm has offices in Michigan (Ann Arbor and Royal Oak); Illinois (Chicago and Peoria); Las Vegas, Nevada; and Los Angeles, California. Howard & Howard’s major areas of practice include: bankruptcy and creditors’ rights; business and corporate; commercial litigation; employee benefits; environmental; estate planning; franchising; intellectual property; labor, employment and immigration; mergers and acquisitions; real estate; securities; and tax. Our distinguished backgrounds provide us with a solid understanding of the industries we serve, including, automotive and industrial; cannabis; commodity futures; construction; energy and utilities; financial services; gaming; healthcare; and hospitality. For more information, please visit the firm’s website at www.howardandhoward.com.